The WIP Aged report shows how old your work in progress (WIP) is. WIP is the value of costs on a job that haven't yet been ticked off against a sales invoice. Seeing how long that value has been sitting unbilled helps you spot jobs that need invoicing, chase stalled work and give finance a clearer picture at month end.
This article explains how to read the WIP Aged report and what each of its options does.
How WIP Aged relates to WIP Retro
WIP Aged uses exactly the same data selection as the WIP Retro report. Both reports decide what counts as WIP in the same way, so the total WIP for a job or phase is identical in each, as long as you run them with the same settings.
The difference is the breakdown. WIP Retro gives you a single WIP value per job or phase. WIP Aged splits that same total by age.
For how data is selected and how WIP is defined, see Understanding the WIP Retro report.
Reading the aging columns
By default, WIP Aged breaks WIP down by how many days ago each cost was dated:
- Current: WIP dated in the past 29 days.
- 30 days: WIP dated 30 to 59 days ago.
- 60 days: WIP dated 60 to 89 days ago.
- 90 days: WIP dated 90 days ago or more.
The report counts days, not calendar months. That means you can run it mid-month and still get an accurate age for every cost.
Reading the final three columns
The last three columns sit after the aging columns:
- Value column: shows the quoted price or total recommended charge by default. Depending on your options, this can show staff charge or client order number instead.
- Future PO: purchase orders dated after the cut-off.
- Invoiced: the value invoiced on the job. If you use revenue recognition, this shows Deferred instead. Find out more about Revenue recognition.
Report options
These options are specific to WIP Aged. Use them to narrow the data, swap what a column shows or change the layout.
Filtering what's included
- Only show purchase values: reports purchase WIP only. Time and materials are ignored.
- Only jobs which are in at the cut off: leaves out jobs with a start date after the cut-off date. You'll rarely need this, as costs aren't normally added to jobs that haven't started.
- Exclude jobs with draft invoices: removes any job with a draft invoice from the report entirely.
Changing the value column
These two options only affect the PDF version of the report.
- Show staff charge rather than quote / recommended charge: replaces the quoted price or total recommended charge with the total staff recommended charge for the job, not just the WIP portion.
- Show client order number: replaces the value with the client's order number.
Changing the layout
- Show 120 days: removes the Future PO column and adds an extra aging column for 120 days.
- Split WIP by cost type: breaks each column's total into purchase, time and material values, similar to WIP Retro. This option is for exports only.
- Show sub totals only: hides the job and phase detail and prints only the sub-totals, grouped by whatever you've chosen in the Sort order drop-down.
Tips
- Run WIP Aged and WIP Retro with the same settings as a quick check. The totals should match. If they don't, the settings differ.
- Keep an eye on the 60 and 90 day columns. Value sitting there is often a sign of a missed invoice or a job that should be closed.
- Use Show sub totals only with a client or account handler sort order for a clean summary you can drop straight into a board pack.
- Build WIP Aged into your month end.