The estimate screen within a job or phase gives you one place to see planned hours, book time in the calendar, and check how much of the budget is left. It matters because it stops teams overbooking a phase, or missing hours that were promised but never scheduled.
Use it whenever you're planning work, adding a new estimate, or checking whether a phase still has time to book.
This article covers how to view and create time estimates, add calendar bookings against them, and read the booking summary that tells you how many hours are left.
Viewing existing time estimates
The screen lists every existing time estimate for the phase you're working on. If your organisation uses two-tier jobs (jobs with an extra level of phases, called stages), estimates are also broken down by stage.
Find out more about how this works in Two-Tier Jobs.
Creating a new time estimate
You don't need to leave this screen to add a new estimate.
- Click Add Estimate.
- Set the details for the new line, including the Staff Team, if you want to restrict the estimate to a particular team from the outset.
Find out more about the wider estimating process in Creating an Estimate.
Creating a calendar booking from an estimate
Once an estimate exists, you can book the time straight into the calendar without switching screens.
- Switch from the full estimate view to Time and Bookings.
- Expand the estimate line you want to book against.
- Click Add Booking.
This creates a resource booking linked to that estimate. See Booking Form for the full detail on filling in a booking.
Understanding booking summaries
Before you add a new booking, it helps to know how much time is already accounted for. Click the option above the list to display booking summaries. The display then changes to show, per estimate line:
- Hours: total hours estimated.
- Current bookings: total hours in current calendar bookings.
- Timesheets: total hours logged on timesheets, including pending ones.
- Remaining: estimated hours less current bookings and timesheets.
For example, a phase has a one-hour estimate. A booking for that hour is made today, and half an hour is already on a timesheet. Today, the summary shows 0.5 hours remaining. Tomorrow, once that booking falls into the past, the same 0.5 hours still shows as remaining to book, rather than 0.5 hours over budget. The figure reflects what's left to plan, not what's gone wrong.
Switching between production and financial views
By default, the column headings show production numbers: estimated, booked and remaining hours. If you want to see the financial side instead, click the drop-down arrow above the list and switch to the view showing cost and recommended charge.
The recommended charge is worked out using your rate card settings.
Booking or viewing time via the Actions button
The Actions button opens the calendar bookings interface directly from this screen. Use it to:
- view all existing bookings for the job or phase
- create new bookings without going through an individual estimate line
See Booking and viewing from Job or Phase for more on this view.
Tips
- Turn on Display Booking Summaries before adding new bookings, so you don't overbook a phase without realising.
- Remember that a "remaining" figure staying steady after a booking's date passes is expected behaviour, not a fault.
- Set the staff team on an estimate early if you plan to report or filter by team later.
- Switch to the financial view when you need a quick read on cost and recommended charge without opening a separate report.