A resource record tells Synergist who can enter timesheets and who can be given work. It controls each person’s default charge code, their cost and charge rates, their calendar colour and the hours used to measure their capacity and utilisation. Getting it right means accurate job costs, reliable capacity reporting and fewer missing timesheets.
This article explains how to set up a resource record and what each setting does.
What is a resource
A resource is a user who enters timesheets or can be assigned work. Work reaches a resource in two ways: directly through an estimate, or through resource bookings in the calendar.
A resource record is usually created at the same time as a new user account. It is optional. If someone will never enter time or be allocated work, they do not need one.
How to open a resource record
- Go to File maintenance.
- Select Users & resource.
- Open the resource you want to edit, or create a new one.
The record is split into tabs. Most of the setup happens on the Details tab.
Setting up the Details tab
The Details tab holds the core information for the resource. Work through the sections below in order.
Default charge code
A charge code is the type of work time is recorded against, such as design or account management. The default charge code is always available to this resource and is selected automatically when they enter a timesheet.
Most setups let the resource pick a different charge code during timesheet entry. If your system restricts timesheets to default charge codes, they cannot change it.
Find out more about Charge Codes.
Cost and charge rates
You can set cost and charge rates for an individual person rather than taking them from their department or charge code. This is useful when two people doing the same work cost the business different amounts.
To set a resource level cost rate:
- Choose a currency from the Currency used for time costing drop-down.
- Tick Resource level costing.
- Enter the rate in the Cost rate box that appears.
Resource level costing works with your base currency too, so you do not need a foreign currency to use it.
Resource level charging works the same way and sets a charge-out rate for this person that is used regardless of the charge code selected during timesheet entry.
Rates can be set in several places in Synergist. See Cost and charge rate hierarchy to understand which rate is used when.
Calendar colour
Use the colour picker to choose how this resource’s bookings appear in the calendar. Booking colours can also be set elsewhere, and a hierarchy decides which colour wins.
See Resource bookings colour coding.
Start and end dates
Start and end dates tell Synergist when a resource is available. Reports treat a resource as having zero availability before their start date and after their end date.
Always add an end date when someone leaves. It keeps your capacity figures honest.
Freelancers
Freelance resources need some extra setup. See Setting up freelancers.
Calendar loading
Calendar loading is the maximum number of hours that can be booked for a resource before they reach 100% and show as red. Synergist uses a system default, but you can enter a different value for this person.
This is useful for part-time staff or anyone with reduced capacity. You will see the effect in the loading view of resource bookings.
Find out more about the Loading view in resource bookings.
Hours required and target hours
These two figures drive several dashboards and standard reports.
- Hours required: the hours this resource should record each week. Synergist uses it to flag missing timesheets.
- Target chargeable hours: the chargeable hours you expect from this resource. Synergist compares it with actual time to measure utilisation.
Target chargeable hours feed the Dashboard - Capacity and the staff utilisation report. Hours required feeds the Missing timesheets report.
Setting normal working days
Resources can enter time on any day, including weekends. The weekly timesheet view shows non-working days in a different background colour so they stand out. By default, Saturday and Sunday are non-working days.
If someone works a different pattern, such as not working Mondays, set their working days here.
- On the Details tab, tick Specify days normally worked.
- Tick the days this person normally works.
- Untick the days they do not.
- Save the record.
Excluded days display in the same way as weekends.
Setting up resource skills
Resource skills control which charge codes a person can use. They also let you set person-specific rates for particular charge codes.
Restricting charge codes
To limit a resource to certain charge codes, first switch on Charge code is resource skills restricted in Company settings > Switches. Once it is on, only the charge codes listed on the Resource skills tab are available to this person.
- Open the Resource skills tab.
- Add each charge code this resource should be able to use.
- Save the record.
Setting rates for specific charge codes
You can also enter a cost or charge rate against any charge code on this tab. This does not need the company setting above. Rates set here apply in all setups, subject to the [Link: Cost and charge rate hierarchy].
Viewing team skills
Team skills work like resource skills but are set at team level. They can limit the charge codes available during timesheet entry and override the cost rate for a charge code.
The Team skills tab on a resource record is view only. It gives you one place to see every resource skill and team skill available to that person. Team skills are set up and maintained in the team record.
Tips
- Set an end date the day someone leaves. Without it, capacity reports assume they are still available.
- Use a custom calendar loading for part-time staff, so their bookings turn red at the right point rather than at a full-time limit.
- Set daily hours before specifying working days. The weekly totals then recalculate for you.
- Check the Team skills tab before adding resource skills. The charge code may already be available through the person’s team.